4 min read
Start with the Papers the Insurer Already Owes You
Before you argue about the number, get the documents that show how it was reached. Florida law requires the insurer to produce most of them.
- A copy of the estimate. The insurer must send you any detailed estimate within 7 days after its adjuster generates it. Fla. Stat. § 627.70131(3)(e) (2026).
- A written explanation. The insurer must give you a reasonable written explanation of the policy basis for its payment. If it pays less than its own detailed estimate, it must explain the difference in writing. § 627.70131(7)(a).
- Notice that a payment isn't final. A payment that isn't the full and final payment must say the insurer is continuing to evaluate the claim and may issue more. § 627.70131(6)(b).
- The claim log. The insurer must keep a record of all claim activity, including inspections, communications, and decisions. § 627.70131(4)(a).
Find Out Which Kind of Gap You're Dealing With
A low payment is rarely one thing. It is usually a combination of the following, and the evidence you need depends on which one applies.
- Scope. The estimate covers fewer repairs than the damage requires, or leaves out hidden damage found once work begins.
- Pricing. The unit prices for labor and materials don't reflect what repairs cost in your area.
- Depreciation. More was deducted for age and condition than the item's actual condition supports.
- Matching and code. Only part of a continuous surface is included, or required building code upgrades are left out.
- Deductible. The amount applied isn't the one on your declarations page, or was applied to a structure that wasn't damaged.
Compare the Estimates Line by Line
Place the insurer's line-item estimate next to your contractor's and compare them item by item. For each difference, write down whether it is scope, price, depreciation, deductible, or coverage. That single exercise usually isolates the real dispute and makes the conversation with the insurer much more specific.
Put the Difference in Writing
- Send a written supplement. Attach the contractor's estimate, photographs, and a line-by-line explanation of what the original estimate omitted.
- Ask for the basis of the decision in writing. Request the specific policy language the insurer relied on and the adjuster's reasoning.
- Request the adjuster's log. Fla. Stat. § 627.70131(4)(a) requires a log of all claim activity.
- Confirm the payment isn't final. If the insurer is continuing to evaluate the claim, that must be stated in writing under § 627.70131(6)(b).
- Provide requested documents promptly. Deadlines pause if material information you were asked for isn't provided within 10 days, under § 627.70131(8)(b).
Check How the Payout Was Calculated
Sometimes the estimate is right and the calculation is the problem. If the insurer paid actual cash value rather than replacement cost, or applied a roof deductible, the payment can be far below the repair cost even when nothing was left out of the scope. ACV vs. RCV: How Your Insurance Payout Is Calculated walks through the math.
Watch the Deadline for Additional Damage
New damage found later must be reported as a supplemental claim within 18 months after the date of loss. Fla. Stat. § 627.70132. Damage discovered behind a wall during repairs still has to be reported within that window, so document it as you find it rather than at the end of the project.
When to Have the File Reviewed
If the insurer won't explain the payment in writing, keeps asking for documents it already has, or has not responded to a written supplement, the file is worth a review. A short review of the estimate, the correspondence, and the policy usually shows whether the gap is a documentation problem or a coverage dispute, and what the next step should be. Why Insurance Claims Get Delayed or Undervalued covers the patterns behind both.